Capital Projects

The Capital Project Improvement Proposal was approved by district voters on December 12, 2018.


Capital Project Phase II Construction News and Updates

With the arrival of Summer 2020 came the official start of Phase II Construction on our Capital Improvement Project. Through approximately the next two years, there will be continuous progress and completion of the many components of Phase II. Now that construction is happening on an ongoing and consistent basis, there’s more to show you! This means we’ll be bringing you more frequent updates that you’ll find here as they happen, including videos and pictures of construction progress.*

To see all of our Pre-Phase II Construction Updates & News, visit our Capital Project News Archive page.

*Given the rapidly changing nature of the COVID-19 pandemic there is a possibility of unexpected delays in construction or our own updates. If this is the case, we will let you know.
 

(September 21, 2020): Pictures: Short September Construction Update! 

As we near the end of September, enjoy a small collection of recent photos from Phase II Construction in the Middle and High School. Students have returned for the school year, but thanks to the safety plan we created with our Project Manager, Turner Construction, site work has continued moving right along in both buildings without disrupting our student’s daily routines.

Check back soon for our next site visit video update in the near future!
 


(August 24, 2020): Video & Pictures: August Construction Updates

A lot has happened in Phase II Construction since our last Capital Improvement Project video update in July! Join Ichabod Crane Superintendent, Suzanne Guntlow, and Christian Davila & Sarah Plitnick from Turner Construction as they walk you through some of the progress in the video below.

You can also look through a number of pictures arranged in chronological order that show the development of Phase II progress at the Middle and High School through the month of August.


(August 20, 2020): Capital Project & School Reopening: A Safety Overview

Capital Project Phase II Construction has been moving along smoothly through the summer months and we’re happy to announce that it will continue uninterrupted with the start of the school year. We have been working with our Project Manager, Turner Construction, to create a safe and minimally disruptive plan as students begin returning to the building. We invite you to read a quick rundown of the safety procedures and precautions that the onsite contractors will follow this fall and through the upcoming year. Click to learn more.


(July 24, 2020): MS Temporary Classroom Progress and Walls Going Up in HS

Your weekly check-in on Phase II Construction as it continued moving smoothly over at the Ichabod Crane Middle and High School. Below you’ll see a lot of the progress on our temporary classrooms that students will use during construction on particular middle school pods/wings. Over at the high school, you’ll see that wall framing is happening in the Guidance Suite and you’ll even see the framing for the darkroom walls in the back of a room in the Art Suite.


(July 20, 2020): Exective Summary Report on Phase II Construction, June 2020

The June 2020 Capital Project Executive Summary Report on Phase II Construction is publicly available below:

 

 

 


(July 16, 2020): More Progress in the MS 100 Pod and HS Guidance & Art Suites

Construction in the Ichabod Crane Middle School 100 Pod and High School Guidance & Art Suites continues moving right along! More wall framing continued this past week in the Middle 100 Classroom Pod, as well as in the HS Suites. You won’t recognize some of these familiar places and rooms yet, but soon enough they’ll be better than ever!

You’ll also see a view of the construction staging area near the Maintenance Building below and more of the temporary classrooms being set-up in the Middle School Gym.

 


(July 9, 2020): Video & Pictures from MS 100 Pod & HS Suites

On July 8, Turner Construction’s Project Superintendent for Ichabod Crane, Christian Davila, and Ichabod Crane’s Superintendent of Schools, Suzanne Guntlow, gave us some of the latest construction updates.

There are six Prime Contractors involved in overall Phase II Construction:

  • Turner Construction Company – Ichabod Crane School District Construction Manager
  • Aktor Corp. – Abatement Contractor
  • Bast Hatfield – General Contractor
  • Clune Electric – Electrical Contractor
  • Collett Mechanical – Mechanical Contractor
  • Technical Building Services – Control Contractor

Our abatement contractor, Aktor Corp., broke ground for asbestos removal in the Ichabod Crane Middle School 100 Pod on June 3 and then broke ground for abatement the following day at Ichabod Crane High School’s Guidance & Art Suites.

After about two weeks, Aktor wrapped up abatement in both buildings for now and our general contractor, Bast Hatfield, moved on to the selective demolition process that they are now close to completing. Selective demolition entails removing walls, ceilings, carpeting and any other existing building components needing removal based on architectural drawings. You can see several images from the selective demolition process in the Middle and High School buildings below.

With those components removed, chalk is then being used to frame outlines of where the walls of the new classrooms and suites will go. In the Middle School 100 Pod, many walls are already starting to go up and the same will soon happen in the High School Guidance suites area. You can see some of them going up in the pictures below, as well as some of the walls for the temporary Middle School classrooms during construction.

Construction on these parts of the Capital Project is right on schedule and, in fact, our prime contractors got a small head start on the process because students were not in the buildings during June.

An FYI to any visitors driving through campus, you’ll see the fenced-off construction staging area located next to the Maintenance Building for the remainder of construction. This area will house construction equipment and the shared construction trailer.

To ensure everything is on track and address any issues that may come up, we’re also holding bi-weekly meetings between project architects (CSArch), construction management (Turner Construction), the district Facilities Manager, district administrators and some of our board members. These meetings will continue for the remainder of the construction.